Engineering
and Operations Home Page | Completed
Projects | Projects
Under Construction| | Projects
in the Planning Stage | Disaster
Response Information | Water
Testing and Treatment
Engineering and Operations Information
Completed Projects
Plant 28 Upgrade
The District replaced the original well at Plant 28
with a new 20-inch well in the early 1970s. This new well was
deeper, and its larger casing allowed it to produce considerably more
water. However, the surrounding distribution system had a limited
carrying capacity, so the District initially installed equipment to
limit the wells production to about 700 gallons per minute.
During the 1994 annual water quality-testing program,
a contaminant known as tetrachloroethylene or perchloroethylene appeared
in several wells in extremely low concentrations. Fortunately, the
level detected was considerably below the maximum contaminant level
(MCL), but it required close monitoring.
In
1995, the need for additional water prompted the District to update
the well to increase production to 1000 gallons per minute. This,
in turn, began stressing the old and corroded piping system, causing
it to leak. Test results in early 1998 indicated the contaminant level
was approaching the MCL and the well was turned off. While the well
was off, the District installed a granular activated carbon system
to treat the water. This allowed the well to be used again by late
summer 1998. The installation of this system and related costs amounted
to over $300,000. A well upgrade and water system enhancement program
was also implemented. In early 1999, the District had a contractor
replace nearly all of the pipes in the vicinity of Plant 28. The District
also installed new well equipment to increase its capacity to 2000
gallons per minute. The enhanced system was returned to service in
May 2000.
Plant 99
The District had some work done on its 500,000 gallon
reservoir tank at Plant 99, which is located west of La Praix Avenue
and north of 28th Street. A consultant inspected the tank and the
District contracted with Pacific Titan to do the necessary repair
work, bringing the facility up to current OSHA standards.
An additional access door and safety railing were installed,
and an access ladder was brought up to code. The silicone-alkyd coating
used on the outside of the tank has a glossy finish which is designed
to repel UV rays, allowing it to last a good 20 years. The coating
is a nice grouse-tan color, which blends nicely with the environment.
The interior of the tank was also sandblasted and recoated. The entire
cost of the project was $83,400.
Philip
A. Disch Surface Water Treatment Plant
In late 2000, the District contracted with Chlortek,
a division of Severn Trent Services, to install an on-site sodium
hypochlorite (liquid chlorine) generation unit at its treatment plant,
located north of Highland Avenue, just east of the Crosstown Freeway.
The purpose of this work was to eliminate the use of gas chlorine
at this facility. The new unit produces liquid chlorine with a concentration
of .8% (household bleach has a concentration of 5%), which makes the
facility safer for the operators and surrounding population. The work,
costing $129,500 began October 10, 2000 and was completed on December
11, 2000.
Plant
125
Construction has finished on a new reservoir to replace
a 50,000 gallon reservoir that is located south of Greenspot Road
near the Santa Ana River in the City of Highland. The old reservoir
was damaged due to corrosion and age, and the cost to repair it would
have exceeded replacing it. Accordingly, the District removed the
old reservoir and replaced it with a new reservoir of the same type.
The cost of installing the new reservoir was just under $40,000.
Plant 147
Due to future construction of Metropolitan Water Districts
Inland Feeder Pipeline Project, the Districts Plant 121 well
has been replaced by a new well. The well was located west of the
intersection of Abbey Way and Church Street. Design and construction
costs are being paid for by Metropolitan Water District. The new well
at Plant 147 is located at Abbey Way, about 2000 feet east of Church
Street. The new well was drilled, the casing and gravel pack were
installed and the well was test pumped for proper sizing. We equipped
the well with a pump and motor and installed a pipeline to deliver
the water to our distribution system. Construction is complete and
total design and construction costs approached $1,000,000.
|