Baseline Gardens Consolidation
About the Project
BGMWC Map
East Valley Water District has begun the consolidation process with Baseline Gardens Mutual Water Company, to transfer their customers to EVWD water service.

EVWD has received a $6.4 million grant from the California Department of Public Health to design the project and to install pipeline, water meters and new fire hydrants. In previous consolidations, the homeowners joining the District were required to pay for project cost through the formation of an assessment district. However, these grants allow for all of the right-of-way construction to be completed at no additional cost to the customer.

For more information about this project contact the District Engineering Department at (909) 888-8986.

Project Construction Timeline
  • July 2013- Construction Begins
  • July 2014 - Estimated Construction Completion

Project Background
  • August 16, 2010- BGMWC receives State Order to Correct Non-Compliance
  • November 18, 2010- BGMWD Shareholder Meeting to conduct a survey with results in favor of consolidation with EVWD
  • January 2011- EVWD initiates Preliminary Design Study based on November survey results
  • May 24, 2011- BGMWC and EVWD execute an Agreement to Transfer Service requesting that EVWD assume operation and control of BGMWC water system
  • June 25, 2011- BGMWC Board passes a resolution authorizing application with EVWD for State funding
  • August 4, 2011- EVWD initiates project design
  • August 23, 2011- EVWD Board passes resolution authorizing application with BGMWC for State funding
  • October 25, 2011- EVWD consucts a Public Hearing to adopt CEQA
  • October 31, 2011- EVWD submits grant application for project funding
  • December 18, 2012- EVWD receives State Funding Agreement letter for $6.4 million in infrastructure costs
  • January 23, 2013- EVWD Board passes resolution authorizing the execution of a funding agreement with the State.
  • February 9, 2013- BGMWC Shareholder vote to move forward with State funding
  • February 15, 2013- EVWD executes California Department of Public Health funding agreement
  • March 2013- Field Crews Locate Current Utilities/ Project Design Complete
  • May 2013- Construction Bid Results