Starting mid May 2020 to October 2020, Del Rosa Dr. from 5th St. to Baseline will be closed for construction. Crews are installing 6,000 linear feet of new sewer line that will tie into the SNRC. For more information please contact (909) 889-9501.

Continue Reading...

Oct 08

The SNRC Adds Another Resource to Create Renewable Energy and Offset Operating Costs

Posted on October 8, 2019 at 8:04 AM by Roxana Morales

Working to “Make Every Source a Resource” and striving toward a more sustainable future, East Valley Water District (District) Board of Directors approve the addition of state-of-the-art co-digester technology at the Sterling Natural Resource Center (SNRC). This enhancement represents a significant improvement to the project by allowing the SNRC to produce enough renewable electricity to meet the facility’s energy needs, with additional electricity transferred onto the energy grid.  

Continue Reading...

Aug 19

15 Million Pounds of Concrete Poured into the Aeration Basin's Foundation

Posted on August 19, 2019 at 8:46 AM by Roxana Morales

Crews pour 15 million pounds of concrete into the aeration basin's foundation.

Continue Reading...

Aug 19

Crews Lay About 150,000 Pounds of Reinforcing Steel for the Aeration Basin’s Foundation

Posted on August 19, 2019 at 8:15 AM by Roxana Morales

Progress continues at the Sterling Natural Resource Center construction site. Crews have laid about 150,000 pounds of reinforcing steel for the aeration basin’s foundation. 

Continue Reading...

Aug 16

Walls Up! Crews Install the Influent Pump Station's Wall

Posted on August 16, 2019 at 4:32 PM by Roxana Morales

With the steel foundation and concrete in place, crews are now focusing on assembling the SNRC’s influent pump station walls. 