Walls Up! Crews Install the Influent Pump Station's Wall

Posted on August 16, 2019 at 4:32 PM by Roxana Morales

With the steel foundation and concrete in place, crews are now focusing on assembling the SNRC’s influent pump station walls. Following a similar process as the foundation, reinforced steel is strategically arranged to ensure concrete walls keep their shape. 

Influent Pump Walls Primary

Due to their size and height of 30 to 35 feet, each wall has to be lifted using a crane and carefully put in place. 

Influent Pump Walls Lifted

Influent Pump Walls Placed